|
Profiles of Multifamily
Weatherization
Projects
Weatherizing multifamily
buildings can yield substantial savings for both owners and occupants,
according to the results of case studies of buildings throughout the country.
The U.S. Department of Energy (DOE) and Oak Ridge National Laboratory (ORNL)
recently took a close look at retrofit programs in the northern cities
of New York, Chicago, St. Paul, Springfield, MA, and Seattle. In each city
at least one building was selected for evaluation. In addition Home
Energy asked representatives of the City of Austin to describe their
multifamily program, which focuses on saving cooling energy.
The profiles presented here reveal some important
lessons learned regarding both the assessment of potential savings and
the effectiveness of various weatherization options.
A Tale of Five Cities
by Larry Kinney, Tom
Wilson, and Michael MacDonald
About 20,000 dwellings in
multifamily buildings were retrofitted under the Weatherization Assistance
Program in 1990. To find out in detail what work is being done in the field,
DOE and ORNL evaluated five cities that had a high number of retrofits.
Before describing the programs in each of the
cities, we want to summarize the conclusions drawn from examining them.
Energy Audits
We found that the quality of energy audits in
larger multifamily buildings increased significantly from 1989 to 1994
in some areas, especially in those using computerized audits such as New
York's EA-QUIP program. However, improved estimates of savings are needed
to encourage more owners to invest in energy efficiency and lenders to
finance that investment.
Investment Decision Method
The studies found that some programs examine
the amount of energy a building uses and how much that energy costs before
deciding what level of investment in energy efficiency is appropriate.
Other programs undertake retrofits based on recommended measures for particular
building configurations. It is important to analyze existing energy consumption
and costs before recommending measures for a building in order to keep
the ratio of benefits to costs greater than 1.
On the other hand, the weatherization effort
in Seattle is achieving significant energy savings, although benefit-to-cost
ratios are often less than 1. Because electricity rates in Seattle are
a little less than half the national average (4¢ versus over 8¢),
benefit-to-cost calculations might only allow people to save half as much
money as the national average, assuming a direct relationship between investment
and energy savings.
Comprehensive Weatherization
Our results reaffirm those of a study of 191
buildings conducted several years ago at Lawrence Berkeley National Laboratory.
In buildings with electric heat, expensive shell measures must typically
be installed to achieve high savings (as was the case in Seattle). But
in buildings that are centrally heated with fuel other than electricity,
it is often possible to achieve high savings at low cost. The options for
doing this include control system changes, modification or adjustment of
the central heating plants, and ensuring that operators understand the
proper functioning of controls.
Savings in water consumption and in energy used
by domestic hot water systems are also important and can be achieved cost-effectively
in many multifamily buildings.
Replacing windows depends heavily on owner investment.
The energy savings from new windows can be fairly important, but the cost
is very high. Owners receive benefits beyond energy savings, however, that
can induce them to make the necessary investment--increased property value,
neighborhood improvement, and tenant and landlord satisfaction.
Building shell measures can also save energy,
but building configuration and outside investment play important roles
in cost-effectiveness. Taller buildings tend to benefit more from sealing
air leakage paths such as those to or from chases and core areas. Of course,
for centrally heated buildings, no amount of shell improvement will translate
into realized savings unless the heating plant is operated in a controlled
fashion, responsive to temperature needs of the building occupants.
New York City
New York City
has 126,000 multifamily buildings with more than 1.9 million apartments.
Most of the building owners pay high energy bills, due to inefficient buildings,
poorly maintained and controlled heating systems, and high prices (natural
gas is 72¢ per therm and electricity 18¢ per kWh). In a typical
year, the 22 weatherization agencies in the New York metropolitan area
manage weatherization jobs on over 250 buildings containing 8,000 to 10,000
apartments.
The audit used in New York covers both mechanical
and architectural options, but in practice the most important savings opportunities
flow from work in the boiler room and the heating distribution system.
Air sealing of the building envelope concentrates at the top and bottom
of the common areas and usually includes interior doors to apartments.
Insulation is used on distribution system pipes and in attics, but seldom
elsewhere. Only rarely does the audit find that window retrofits pay for
themselves. However, many building owners are willing to pay at least some
of the cost as part of their matching investment, citing the benefits of
neighborhood improvement, increased building value, and better tenant relations.
|
Crown Heights Jewish Community
Center, 1082-1096 President Street, Brooklyn, NY
|
This Brooklyn block is like hundreds of others
in the borough that were built in the first half of the twentieth century:
four-story, heavy brick construction apartment buildings in the middle
of the block, with taller apartment buildings on each corner flanking the
row.
Two pairs of individual apartment buildings (each
a 20-unit walk-up) were the subject of weatherization measures. Each set
of two buildings encloses a central courtyard, creating a rectangular donut-shaped
building plan. The average apartment size is 518 ft2 with 9-ft ceilings.
Most apartments have windows on one side only, and these are the original
wood double-hung units with no storm windows.
Weatherization Measures
Like all multifamily building audits in New York
City, this one was conducted with the aid of recent billing records and
EA-QUIP, a computer-based analytical package (see "Confessions
of an `Addicted' Auditor," HE May/June '94, p. 29).
The weatherization agency upgraded the heating
systems and switched to a lower cost fuel as part of a daring heating system
retrofit. Originally, each of the four buildings had heat and domestic
hot water (DHW) supplied by its own 1.2 MMBtu/h output natural gas-fired,
atmospheric one-pipe steam boiler. The heating-system retrofit consisted
of replacing all four units with one forced-air, steel-tube steam boiler
with a 4.2 MMBtu/h output. It provides heat and DHW for all four buildings.
The new unit burns #6 fuel oil, which costs 42%
less than natural gas in New York. The new control system includes a standard
heat timer; however, a hot water mixing device was also installed. The
mixer continually senses return water temperature from each building and
automatically mixes the required cold water to maintain each building's
minimum heat requirement while providing on-demand DHW.
The boiler replacement included interconnection
of the basement area supply and return lines as well as extensive pipe
insulation, sealing of miscellaneous pipe openings and window openings,
and whitewashing walls and ceilings.
Reduction of heat loss due to the stack effect
was addressed by controlling the access door opening at the top and bottom
of the central stairwell and by weatherstripping apartment entry doors.
The building's lower entrance doors are typically kept closed and locked
for security reasons. However, before weatherization, the roof door did
not lock and was very often left open. The roof door is now weatherstripped
and closed. A burglar alarm system deters unauthorized access.
Energy-efficient fluorescent lighting was installed
in the hallways and in the kitchens and bathrooms of each apartment.
Weatherization work was augmented by client education.
The auditors informed the building residents of the nature of the work
and of the importance of keeping doors closed. Education was also provided
to the building superintendent, making sure he understood the new heating
system and could manage it correctly.
Savings
The combined consumption rate in the four buildings
was 30 Btu/ft2/HDD for a total normalized annual consumption (TNAC) prior
to weatherization of 8,400 MMBtu. The postweatherization consumption rate
was 26 Btu/ft2/HDD, a reduction of 16% in heating-only normalized annual
consumption (HNAC).
These numbers are more impressive when the reduction
in cost of fuel is considered. Natural gas from the local utility costs
approximately $7.20 per MMBtu, while #6 fuel oil costs $4.20 per MMBtu.
The calculated annual savings is $32,500. The total cost of the retrofits
was $99,500, and the benefit-to-cost ratio, based on a 20 year life and
4.7% real discount rate, is 4.5.
Springfield-Holyoke
The multifamily
housing stock that was the subject of the Massachusetts case study is composed
primarily of wood-framed, brick veneer buildings with flat roofs. These
structures are built in a variety of early twentieth-century architectural
styles and have interior light and ventilation shafts or building configurations
that include courtyards. The attics are typically below a low-pitched flat
roof and are accessible only through an interior trap door, which is usually
installed during weatherization.
|
47-49 Vernon Street,
Holyoke, Massachusetts
|
This three-story, wood-framed brick veneer building
was built early this century by a local manufacturer to house employees.
It contains nine apartments (475 ft2 each) and one commercial unit (which
is not in use). Individual heating and domestic water heating, both gas
fired, are located in each apartment. The heating units are combined with
the cookstove. The heating portion of the unit is controlled by a thermostat
and is vented; however, the cooktop is not vented. The windows are double-hung
wood with vinyl storm windows.
Weatherization Measures
The weatherization crew from the Hampden Hampshire
Housing Partnership paid close attention to the safety of the mechanical
and electrical systems. They inspected the knob-and-tube wiring throughout
the building, paying special attention to areas that were to be insulated,
and made electric wiring and panel box repairs before starting other work.
They inspected the combination heater-cookstoves in each apartment and
cleaned and tuned several that were burning inefficiently. Pre- and postweatherization
tests for carbon monoxide are routinely done on all weatherization jobs
in Massachusetts (see "Carbon Monoxide from Ovens,"
p. 18). Gaps around the vent stacks of domestic water heaters, which are
also located within the living space, were repaired.
The crew did blower door testing in conjunction
with insulation and air sealing work. They tested one apartment on each
floor of the building before and after weatherization measures were installed,
and measured individual apartment air leakage reductions ranging between
300 and 1,000 cubic feet per minute at 50 pascals of pressure (cfm50).
(A 1,000 cfm50 reduction would likely reduce annual fuel bills by about
$50/unit.)
The crew made it a priority to control heat loss
at the bottom of the building envelope in the basement area. They used
spray foam to seal the basement sill, basement windows, and mechanical
penetrations, and blocked bypasses with blue foam board. They doubly secured
batt insulation at the basement ceiling with both staples and wire supports.
The most expensive item was storm windows, which
accounted for 37% of the total cost.
Savings
The weatherization achieved 28% savings in natural
gas, which amounted to $1,200. It cost $9,200 for this nine-unit building
(a benefit-to-cost ratio of 1.6).
Chicago
In Chicago, Illinois,
the weatherization program is run by the city Department of Housing. The
Department has traditionally increased the impact of the DOE weatherization
investment by leveraging additional funds from building owners. Although
the Department pays the full cost of, say, storm windows or a boiler tune-up,
they require a 50% landlord contribution for especially expensive retrofits
such as new primary windows or heating plant replacement.
|
5220 South Drexel
Avenue,
Chicago, Illinois
|
For years, most of the larger retrofit projects
involved city- or HUD-owned structures. The 5220 South Drexel Avenue site
was the first large privately owned building weatherized by the city.
Built in 1926, this four-story, 72-unit building
embraces nearly 56,000 ft2 of living space (about 778 ft2 per apartment).
Originally the Drexel Residence Hotel in the fashionable Hyde Park area
of Chicago, the building is solid brick with 18-in-thick fire walls between
apartments.
The building is very well maintained, and the
owners are both informed about and concerned with energy efficiency and
other critical residential issues (such as lead paint). At present, over
40% of the tenants in this building are disabled, and the owners intend
to convert unused ground floor space into additional apartments in order
to make effective use of the handicapped access to that area.
In this 6,625 HDD climate, the heat and hot water
are supplied by a large 2 million Btu/h input, gas-fired Kewanee steel
fire tube boiler with a gas power burner.
Weatherization Measures
The owner paid 50% of window replacement for
55 apartments and 100% for an additional 5 apartments. The installed windows
are high-quality, double-glazed, vinyl-framed units. Work was completed
by May of 1993, with $29,000 contributed by DOE.
At the same time, the owners installed new doors
for each apartment and new steel fire doors in the stairways.
Savings
Heating-energy usage was cut 27% for a savings
of nearly 10,500 therms of natural gas per year. The bill analysis also
showed an unexplained 10% reduction in anual baseload energy use for a
total annual savings of nearly 12,500 therms.
Such impressive fuel savings and payback from
what was principally a window replacement may seem surprising given the
Brooklyn results. However, in combination with the window replacements,
the new doors contributed significantly to reducing stack effect and air
leakage, thus allowing better control over the building temperatures and
heating system operation. In addition, the building is now less drafty,
maintenance costs are lower, the appearance is improved, and a major source
of lead dust has been eliminated.
If this building were being retrofitted under
the guidelines in place now for the City of Chicago, major retrofitting
of the heating plant would be considered. The present boiler is "getting
thin on the bottom" and demands $1,500-$2,000 per year in maintenance.
Since all domestic hot water is supplied by this boiler, there are also
extreme inefficiencies during summer operation. However, this project demonstrates
that it is possible to get cost-effective savings in large multifamily
buildings through architectural measures, when such retrofits are paired
with careful operation and maintenance.
St. Paul
In the greater
St. Paul, Minnesota, area, weatherization is carried out by the Ramsey
Action Program (RAP). Making extensive use of many technical advancements
of its own and other local research groups and individuals, RAP also uses
a state-sponsored, comprehensive multifamily audit workbook and training
program.
|
Pullman Avenue Buildings,
316 and 332 Pullman Avenue,
St. Paul, Minnesota
|
These two buildings are outwardly identical,
three-story wood-framed structures, owned by the Housing Resource Authority
(HRA). They have brick front facades and stucco side and rear walls. Each
building has six apartments and a total of 8,950 ft2 of living
space (about 1490 ft2 per unit). Prior to weatherization, each had fiberglass
in the walls and 6 in of insulation in the attic. All have through-the-wall
air conditioners and aluminum slider windows with aluminum storms.
Although both buildings were built in the mid-1970s
by the same contractor, 316 has individually metered electric baseboards
in each apartment, while 332 has central gas multizone hydronic heat.
Weatherization Measures
Envelope measures in both buildings included
- Sealing bypasses in the attic.
- Increasing attic insulation from R-22 to R-44.
- Insulating a small crawlspace under the front entrance.
- Installing covers over through-the-wall air conditioners.
In the centrally heated building, the weatherization
program also installed new outdoor reset and cutout controls on the boiler
and added pipe insulation to all exposed distribution lines.
Cost
The electrically heated building, which received
only envelope measures, cost $1,200, while the centrally heated building
received about $1,900 of work.
Savings
These retrofits were particularly interesting
because we could compare two otherwise identical buildings that had different
heating systems, and to which different sets of measures were applied.
The apartments in the electrically heated building (316 Pullman) are individually
metered, which also facilitated an apartment-by-apartment comparison of
pre- and postretrofit fuel use patterns.
In 332 Pullman, where both envelope and heating
system retrofits were applied, the overall energy savings were significantly
greater than in the electrically heated building (95 MMBtu versus 15 MMBtu).
However, higher installation costs in 332 and significantly lower fuel
prices result in a lower benefit-to-cost ratio (2.59 versus 3.92).
Although 316 Pullman showed moderate overall
savings from the envelope improvements, there was wide variation among
individual units. Results for individual apartments can be misleading because
there is inevitable heat transfer among units and occupancy can change.
Nonetheless, the individual apartment consumption data show some important
patterns.
Apartments on the lower floors had lower preretrofit consumption than
those on the top floor. This can be explained by the fact that only the
top floor apartments were exposed to cold ceiling temperatures from the
poorly insulated attic.
After retrofit, the third-floor apartments had
not only the greatest savings but also the lowest postweatherization energy
bills. However, energy use in the first-floor apartments actually increased.
How can this be explained? The attic insulation not only reduces energy
use for the upper apartments but may, in fact, cause these units to overheat
as warm air rises from the lower units. If the overheating is great, the
occupants are likely to open windows to alleviate the situation. This increases
the impact of the stack effect and more heat is drawn from the lower apartments,
thus increasing their energy use.
In extreme cases, such dynamics could actually
lead to a condition where the addition of attic insulation in a multistory
building will increase overall building energy use. In support of
this theory, it should be noted that on the morning we visited these buildings
the outside air temperature was 42deg.F, but the previous day had been
unseasonably warm. We noted during our visit that all of the third
floor apartments in all three buildings had at least one open window.
|
727 Front Street,
St. Paul, Minnesota
|
The 727 Front Street building is a 20-story high
rise with 151 units, owned by the St. Paul Public Housing Agency. Heat
is produced by two 5 million Btu/h dual-fuel Kewanee boilers, which use
oil and gas. These provide multizone, two-pipe steam heat and hot water.
Built in 1970, the building has 112,000 ft2 of conditioned space with a
pre-retrofit calculated energy index of 12 Btu/ft2/HDD.
Weatherization Measures
RAP determined that the most cost-effective energy
savings would come from non-heating season hot water loads and common-space
lighting. All of the weatherization work (completed in April 1991) focused
on the mechanical systems and lighting except for the installation of room
air conditioner covers.
Before this retrofit, boiler condensate, returning at 180deg.F, used
to freeze as it passed the large combustion air intakes for the boiler.
RAP insulated all exposed DHW pipes as well as the condensate return line
from the boiler. The freezing problem was further mitigated through repair
of combustion air dampers, which had been damaged.
RAP installed two Triad front-end modular boilers
(240,000 Btu/h output each) for summer domestic hot water and recommended
that the two larger boilers be run only in winter as staged units. Although
the boilers were subsequently shut down in the summer as planned, during
the heating season the building operator chose to run the two units in
parallel, rather than in a staged sequence as recommended.
RAP replaced incandescent fixtures with fluorescents
in exit signs and stairwells. Existing fluorescent fixtures in the common
areas were retrofitted with new reflectors and high-frequency electronic
ballasts (see "Bright Prospects for Lighting Retrofits,"
p. 41).
Cost
The total installed cost of $39,000 included
$22,400 for lighting retrofits. Proper disposal of old lighting ballasts,
which may have contained PCBs, was funded with a grant from Northern States
Power. The two front-end Triad boilers cost $10,000, and the cost of the
pipe insulation was approximately $900.
Savings
The summer baseload consumption was reduced by
27% for a savings of 245 MMBtu. A lifetime savings of $10,500 and a benefit-to-cost
ratio of 1.04 demonstrates that the retrofit was barely cost-effective,
partly because the building operators failed to utilize the winter savings
potential of staged boiler operation.
The lighting retrofits saved 170,000 kWh per year, approximately 20%
of the electrical consumption for the building. The benefit-to-cost ratio
is 4.0, which illustrates how cost-effective a thoughtfully designed lighting
retrofit can be, especially since lights in common areas are typically
illuminated 12 to 24 hours per day.
Seattle
Most of the 91,000 apartments in Seattle are
in two- to three-story low-rise buildings of 15 to 30 units. A high percentage
of the older housing stock has electric baseboard heaters and electric
water heaters, although natural gas is used for heating and water heating
in newer units, a trend that is supported by Seattle City Light even though
the utility does not sell natural gas.
Summers are mild in the Seattle area, so air conditioning is rare.
However, winters are chilly; Seattle experiences 5121 heating degree days,
slightly more than either New York City or Philadelphia. Nonetheless, wall
insulation in multifamily housing stock is the exception and ceiling insulation
tends to be either absent or minimal. On the other hand, many buildings
are fairly airtight due to local construction techniques and the lack of
flues and chimneys. This, in combination with Seattle's humid climate,
sometimes results in moisture problems.
|
Crescent Arms Apartments,
5201 42nd Ave. South,
Seattle, WA
|
This is architecturally the most unusual multifamily
building encountered in this series of case studies. The Crescent Arms
is built in the form of a fortified annulus, forming five-eighths of a
circle, an architectural feature that allows each of the 37 apartments
in the three-story structure to have light from two sides and cross ventilation.
Each apartment is about 480 ft2.
Like most multifamily buildings in Seattle, the Crescent Arms is a wood
frame structure with a masonry facade. It has poured-concrete partitions
and a flat roof. It appears to be quite tight; before weatherization, conductive
losses from uninsulated walls and single-glazed windows were the largest
paths for heat loss.
Weatherization Measures
Weatherization consisted principally of installing
insulation and new windows. The wall insulation covered 4,200 ft2 at a
cost of 70¢ per ft2. The space between the ceiling and the flat roof
could not be accessed, but it is believed to be insulated. On the other
hand, the floor above the crawlspace could be insulated, so 5,550 ft2 of
9-in unfaced batts were installed, using nails and nylon twine to hold
the insulation in place. Material and labor for this measure cost 72¢
per ft2. To protect water pipes from freezing, 1,215 feet of pipe insulation
was added at a cost of 67¢ per ft.
A total of 239 double-glazed vinyl windows were
also installed at the Crescent Arms at a cost of $57,000, 73% of the total
job cost. Finally, 78 energy-efficient lighting fixtures replaced incandescents
(including 13 100W high-pressure sodium exterior lights to provide security)
at a total cost of $6,000. Adding several air sealing measures and two
power vents brought the cost of the entire job to $77,000, approximately
four times the total annual energy cost for the building.
This weatherization job resulted in a 26% savings in heating energy,
and a fuel cost savings of $3,300.
Larry Kinney is president of the Synertech Systems
Corporation in Syracuse, New York and Tom Wilson is a building scientist
with Synertech. Michael MacDonald is a program manager in Commercial and
Multifamily Building Research with the Energy Division of the Oak Ridge
National Laboratory.
Further Reading
Gerety, F. How to Get the Best from One-Pipe
Steam, New York: City Books (1987), 1 Centre Street, Rm 2223, New York,
NY 10007.
Goldman, C. A., Greely, K. M., and Harris, J. P. Retrofit Experience
in U.S. Multifamily Buildings: Energy Savings, Costs, and Economics, LBL-25248.
Berkeley, CA: Lawrence Berkeley Laboratory, 1988.
Goldner, F., and Judd, P. Building Energy
Use Tracking System. Final Project Report prepared by the Energy Conservation
Division of the New York City Department of Housing Preservation and Development
for the New York State Energy Research and Development Authority, 1989.
Judd, P. The Overheated City: The Prospects for Improved Fuel Economy
in the Multi-family Residential Buildings of New York City. New York:
by the author, 285 Riverside Drive, 3D, New York, NY 10025, 1990.
Judd, P. How Much is Enough: Controlling Water
Demand in Apartment Buildings: American Water Works Association (1993),
6666 West Quincy Ave., Denver, CO 80235.
MacDonald, J. Description of the Weatherization Assistance Program
in Larger Multifamily Buildings for Program Year 1989, ORNL/CON-329.
Oak Ridge, TN: Oak Ridge National Laboratory, 1993.
Rodberg, L., Cherry, R., Cohen, G. Computerization
of the New York State Weatherization Assistance Program, Energy Authority
Report 91-13. Final Project Report prepared by the New York Urban Coalition
Housing Group Inc. for the New York State Energy Research and Development
Authority, 1991.
| The publication of this article in Home
Energy was underwritten in part by the U.S. Department of Energy's
Office of Energy Efficiency and Renewable Energy. |
|